L2, and everything behind the construction wall on L1 are almost demoed. There is new plumbing, heating/cooling, and electrical going in on D2 and D1. The first load of steel support stucture has arrived, the first loads of new concrete forming the ramp and stairs on the D2 level have arrived and you can see the new stair towers rising out of the ground. On the D2 and D1 level you can begin to see how the area will work. The next couple months Inner Loop Road will be a two way from the flag pool running past the Sports and Activities Center, Communication Arts, to the back of Greenquist and Molinaro as we need to close the road along the whole south side of the Union for new sewer and drainage. Check out the picture gallery there are some really neat pictures of the construction!! Keep you posted!
Steve Wallner